Project info:
Construction of coke battery №10
Client
Categories
Location
Project Description:
Coke battery 10-bis with the technology of preparation of tamped charge in combination with the installation of dust-free coke (BVK) and installation of dry quenching of coke (DSTC) at PJSC Alchevsk Coke Plant.
Annual production rate: 1.056 million tons of metallurgical coke per year.
Normative term of construction: 48 months
Actual period of construction: 22 months
Main parametrs of construction volumes:
– reinforced concrete
– metal structures – refractories
– equipment
– Machines incl. LMB
– CDQ equipment
– 49.5 thousand m3
– 24.1 thousand tons – 35.5 thousand tons – 4.88 tons – 1.25 thousand tons – 0.9 thousand tons
– 1,3 thousand tons
SCOPE OF THE PERFORMED WORKS
Development of soil (m3)
Transportation of ground,slag,crushed stone,construction waste (t)
Destruction of rubble, concrete and reinforced concrete structures (m3)
Brickwork (m3)
Dismantling of metal structures (t)
Monolithic concrete and reinforced concrete (m3)
Installation of concrete and reinforced concrete structures (m3)
Installation of metal structures (t)
Refractory masonry (t)
Installation and manufacturing of pipelines (t)
Anticorrosive protection of metal structures (m2)
Installation of equipment (t)